Broad Lane gas upgrade works + road closure: January-September 2018

SGN will be upgrading the underground gas works in and around Broad Lane for nine months in 2018.

From the SGN website:

"We are working to upgrade the gas network in the Broad Lane area of Hampton. 

We are investing £187,000 to replace our old gas mains and services with new plastic pipe to ensure a continued safe and reliable gas supply to the local area. 

In consultation with Richmond Council, we will start work on Tuesday 2 January. Over nine months, our engineers will progress through Cleveland Avenue, Broad Lane and Marlingdene Close in five phases.

To ensure everyone’s safety, we need to implement a temporary road closure, temporary traffic lights and suspend some on-street parking at times. Full details can be found in our project leaflet."

The map below is taken from the project leaflet linked above.

Views: 217