Gas works on Station Road

The existing gas work on Station Road junction with Ormond Avenue is the essential gas work that was delayed previously to allow for other higher priority utility works in the area. 

At the outset, it was unclear whether or not temporary traffic lights would be required as the exact location of the main was unknown prior to excavating the site. 

 

The current traffic management plan does involve 2 way temporary traffic lights with pedestrian facilities as the…

Continue

Added by Richmond Council on June 17, 2016 at 16:00 — 4 Comments